Installation guide · Tubular modules for ultrafiltration

Installation & first start-up
T-CUT UF modules in MBR

Applies to all T-CUT UF tubular modules with FRP housing in crossflow MBR systems – for new installations and for replacing an existing module. Module-specific limits (pressure, temperature, pH, dimensions) are given in the datasheet of your article.

CUT Membrane Technology logo
Contact

!Safety first

Only qualified, trained technicians may install and start up the modules. Read this guide completely before you start.

Release pressure (0 bar) and drain before opening any coupling
Flush the medium out of the whole system before disconnecting lines
Wear eye protection
Wear protective gloves suited to the medium and chemicals
Heavy load: lift with two people or a hoist
Do not stand on modules or place objects on them

Secure the system against unintended restart (lock-out / tag-out) before working on it, and restart only in a controlled way as described in step 5.

1Receive and store

  1. Inspect the deliveryCheck packaging and modules for damage and compare with the packing list. Report damage or shortages to the carrier and to CUT immediately.
  2. Keep the module closedLeave the protective caps on all ports until shortly before installation. New modules contain a preservative (glycerine / sodium metabisulfite).
  3. Store correctlyDark, frost-free, dry and cool, in the original packaging. New modules can be stored this way for up to 2 years – ask CUT for longer periods.
  4. Handle with careA dropped or knocked module can crack internally. Clean the housing only with water or ethanol – never with solvents.
Example moduleWeight dryWeight filled with water
8" × 3,000 mm (e.g. 760617)43 kg147 kg
10" × 4,000 mm (e.g. 760887)115 kg340 kg

2Prepare the system

① Feed ② Concentrate ③ Permeate (top left) ③ Permeate (bottom right) FRP housing with membrane tubes inside
Simplified module: feed and concentrate at the ends, permeate nozzles top left / bottom right. Numbers = connection order in step 4.
  1. Clean the systemRemove solids and oily residues from tank and pipework before a new module goes in. Pre-filtration must be in place (mesh size see datasheet, typically 3 mm).
  2. Check the module typeReplace like with like: a conventional module with a conventional one, a low-energy module (type "e³") with an e³ module – unless the rack has been re-engineered. Same length, diameter and couplings as the old module.
  3. Replacement only: flush and recordStop filtration and rinse the loop with clean water immediately – the old module must not dry out. Record a baseline: inlet, outlet and permeate pressure, feed and permeate flow, temperature, clean-water flux.
  4. Depressurize and isolatePump off, valves closed, gauges at 0 bar, drain the module to be removed. Lock out the pump.

Tip: take a photo of the rack before opening anything – it shows the position of the permeate nozzles, couplings and holders.

3Remove the old module (replacement only)

  1. Confirm 0 bar and emptyOpen the drain and check that the module is depressurized and fully drained.
  2. Open the permeate couplingsRelease both permeate connections and set the couplings aside.
  3. Open feed and return-bend couplingsRelease the couplings at both module ends. Open one module at a time – the others stay in place.
  4. Support, then release the holdersSupport the module (second person or hoist) before opening the last holder clamp.
  5. Lift out, cap and labelIf the old module is to be examined or returned, keep it wet, cap all ports and label it.

Drain first – a filled module weighs three times as much. Never lift or carry a module by its connections.

4Install the T-CUT module

  1. Unpack just before installingCheck for damage, remove the caps, drain the preservative and dispose of it according to local regulations.
  2. Fix the module in the rackUse at least two holders or brackets on the frame and respect the maximum support spacing from the datasheet (e.g. 2,200 mm for 8" × 3 m). Vibrations must not move the module.
  3. Prepare the gasketsUse clean, intact, preferably new seals. A little glycerine helps the couplings slide on.
  4. Connect loosely – in this order① Feed inlet → ② concentrate outlet → ③ permeate outlets.
  5. Check alignmentSeals seated correctly, not displaced, and no mechanical stress on any connection.
  6. Tighten alternatelyClose the couplings by hand as specified by the coupling manufacturer, then the holder clamps. Do not use excessive force – a correctly seated seal is normally tight when hand-tightened.

Never support the module on its connections only – the weight would break the nozzles or the potting.

5First start-up

New modules contain preservative. Rinse it out completely before the first filtration.

AWater rinse
brief
BNaOH rinse
pH 9–10 · 15 min
CWater rinse
until neutral
DDe-aerate
permeate valves open
ERamp up
crossflow, then TMP

Pump and valve sequence

  1. Open the permeate valvesPermeate leaves at zero pressure.
  2. Set the feed sideWith a centrifugal pump: feed valve closed, concentrate valve open.
  3. Start the pump at low speedUse the frequency converter if available.
  4. Open the feed valve slowlyDe-aerate feed and permeate side completely – no hammering, no air pockets.
  5. Raise the crossflow graduallyThen close the concentrate valve slowly to set the transmembrane pressure (TMP).
  6. Check for leaksIf a coupling leaks, depressurize first, then re-seat the seal.

Avoid pressure surges, water hammer and fast valve movements. Keep at least the minimum outlet pressure from the datasheet (e.g. 1.0 bar) at the last module – never allow negative pressure on the feed side, and never exceed the maximum permeate pressure.

Avoid temperature shocks: change temperature by max. about 1 °C per minute, and never switch between media that differ by more than 25 °C.

6Check and record

A good baseline is the basis for judging the module and planning cleaning.

WhenWhat to record
Start-upClean-water flux with clean or DI water (pre-filtered 10 µm) and flux during the NaOH rinse – your new reference
Day 1Inlet / outlet / permeate pressure per module, feed and permeate flow, temperature, flux normalized to 20 °C
Day 7Trend of flux and pressure drop
Within 2 weeksFirst standard cleaning; record clean-water flux again as long-term reference
Day 28Compare with baseline and decide on the cleaning interval
OngoingAt least twice a day: pressures, permeate flow, pressure and turbidity, temperature, pH, crossflow

Solids or colour in the permeate? One or more membrane tubes may be damaged. Sample the modules individually during operation and contact CUT – modules can often be repaired.

Send your start-up log to your CUT contact – we compare it with the datasheet values and help you set up the cleaning plan.

✓Do and don't

Do

  • Fix the module in at least two holders
  • Use clean seals; connect feed → concentrate → permeate
  • Open valves and start the pump slowly; de-aerate completely
  • Keep the membrane wet at all times
  • Record the baseline and the first weeks of data

Don't

  • Carry or support the module by its connections
  • Allow pressure surges, temperature shocks or negative pressure
  • Exceed the pressure and temperature limits in the datasheet
  • Let the membrane dry out
  • Stand on the module or put objects on it
  • Use silicone, ketones, esters, ethers or polar organic solvents

Short stop? Rinse at once and keep the module filled with water. Longer stops, storage and cleaning are covered in the separate cleaning guide.